The Gamka River flooded on Friday, 4 September 2026 and washed away the bulk of Beaufort West's water infrastructure network. During the emergency that followed, the Municipality issued regular media statements on repairs, reservoir levels and the supply of water by tanker. They are summarised below in the order they were issued.

Monday, 7 September 2026

Issued by the Office of the Executive Mayor. The Municipality confirmed that the town remained in a severe state of emergency following the flooding of the Gamka River on 4 September.

  • Technical teams had repaired one smaller supply line to town and had begun slowly filling the reservoirs. Further repair work continued through the day.

  • Emergency water distribution continued according to the schedule announced the previous day, supported by tanker services and JoJo tanks.

  • Relief efforts were coordinated by the Western Cape Department of Local Government with assistance from neighbouring municipalities.

  • Gift of the Givers had deployed two water tanker trucks, and six JoJo tanks were on their way to Beaufort West.

  • The Municipality thanked community members who offered JoJo tanks, space on their properties for tanks, and borehole water for public use.

Residents were asked to cooperate, remain patient and use water sparingly.

9 September 2026: distribution of bottled water

Issued by the Acting Municipal Manager, Frans Sabbat.

  • The distribution of bottled water was done solely by Gift of the Givers; the Municipality had no role or influence in that process.

  • Gift of the Givers was assisting the Municipality with three water tankers to distribute water to communities.

  • The Municipality received an unsolicited donation of 150 units of 2-litre bottled water from SANParks on 8 September 2026, delivered to the municipal offices at 112 Donkin Street.

  • As agreed in the Joint Operations Command Centre, this water would be distributed only to vulnerable groups such as hospitals, old age homes, schools and early childhood development centres, based on need and requests received.

Thursday, 10 September 2026

  • Overall status: regressed. During testing that morning the technical team discovered another break in the 600 mm pipeline, further downstream near the N1 crossing of the Gamka River.

  • Gamka Dam: 100%.

  • Reservoirs (20h00 the previous night): Reservoir 1 at 23% (5.7 megalitres in size), Reservoir 2 at 45% (4.5 megalitres) and Reservoir 3 at 22% (5.7 megalitres).

  • Small pipelines: the Brandwacht pipeline was repaired and pumping water to the reservoirs. It had been damaged by a private contractor; a case was opened with SAPS and the Municipality would invoice the contractor for the costs. The Hans River pipeline was repaired and in commission.

  • 600 mm main pipeline: regressed; further inspection downstream found more damage that had not been detected before.

  • Water supply: tanker services and the refilling of JoJo tanks resumed at 08h00 and would continue until further notice.

  • 250 mm pipeline: functional and able to supply all areas, but testing showed some areas were not getting water, which led to the discovery of the damage on the 600 mm pipeline.

Friday, 11 September 2026

  • Teams were prioritising the repair of the second breakage point on the 600 mm main pipeline, downstream in the Gamka River, and hoped to complete it the next day.

  • The Gamka Dam remained full at 100%.

  • Reservoir levels: Reservoir 1 at 41%, Reservoir 2 at 64%, Reservoir 3 at 33%.

  • The 250 mm pipeline was supplying water through the network, but areas such as Nieuveld Park and Rustdene could experience interruptions.

  • The Brandwacht and Hans River pipelines were repaired and pumping water.

  • Tanker services and JoJo tank refills continued daily from 08h00 until late in the evening.

Saturday, 12 September 2026 (13h00): how the pipelines supply the town

This statement explained which pipeline serves which areas and the state of each:

Pipeline

Areas supplied

Status

250 mm pipeline to Hillside and adjacent areas

Hillside, Toekomsrus and Graceland

Operational and not affected by the flood. Teams connected it to extend supply to the Industrial Area, Essopville, Newlands, Newtown, Hooyvlakte, Rustdene and Nieuveld Park. As it was not designed for this, Nieuveld Park and parts of Essopville and Rustdene could still face disruptions.

250 mm pipeline from the Red Bridge

Normally only Noordeinde and the Upper Town (Bodorp)

Operational.

600 mm main pipeline (Gamka River)

Hospital Hill, the Town, Kwa-Mandlenkosi, Rustdene, Essopville, Newtown, the Industrial Area, Prince Valley and Nieuveld Park

Damaged at Meintjies Street; damage assessed and pipes being ordered.

500 mm pipeline (behind Boland Scrap Metal, Gamka River)

Part of the main supply line

Damaged and under water, inaccessible for repairs. The current priority; recent rain could delay the work.

The network normally runs at 5.5 bar pressure, but with the temporary alternatives only 1.7 bar could be achieved, too low to supply high-lying parts of Rustdene, Nieuveld Park and Essopville. Repairing the 500 mm pipeline was therefore the top priority. The Municipality also warned that spreading false information with the intention of inciting violence or public unrest is a criminal offence under the Cybercrimes Act.

Saturday, 12 September 2026 (13h45): water pressure explained

  • Water pressure is the force that pushes water through the pipelines to homes, businesses and high-lying areas, and is measured in bar. One bar lifts water to a height of about 10 metres.

  • Under normal conditions the 600 mm and 500 mm pipelines operate at 5.5 bar (about 55 metres). The statement compared it to blowing air through a straw: the big pipelines give a strong push, while the temporary smaller pipes give a weaker one.

  • With the alternative arrangements only 1.7 bar was achieved. The missing 3.8 bar was too much to make up, which is why not all areas could be supplied.

  • Thanks to interventions by the engineering teams that reduced the demand on tankers, the tankers could focus on the areas not served by the network.

Tuesday, 15 September 2026 (morning)

  • Overall status: improved. The weather had improved and a private contractor was on site to repair the 500 mm pipeline, with repairs hoped to be completed by the end of the day, followed by testing.

  • Gamka Dam: 100%.

  • Small pipelines: Brandwacht repaired and pumping water to the reservoirs; Hans River repaired and in commission.

  • 600 mm main pipeline: improved. The Bid Adjudication Committee had approved the procurement of the pipe from suppliers the previous day, and the pipe would be ordered that day or the next.

  • Water supply: tanker services and JoJo tank refills continued from 08h00 until further notice.

  • 250 mm pipeline: functional but negatively affected by the damage to the 500 mm pipeline; testing of the network would restart once the 500 mm pipe was repaired.

Tuesday, 15 September 2026 (16h30): 500 mm pipeline repaired

  • The private contractor repaired the 500 mm pipeline by 13h00. The municipal team opened the water flow and began testing, and initial reports were positive.

  • Gamka Dam at 100%. Reservoirs: Reservoir 1 at 32%, Reservoir 2 at 53%, Reservoir 3 at 27%.

  • The Brandwacht and Hans River pipelines were pumping water to the reservoirs.

  • The 250 mm pipeline, together with the 500 mm pipeline, was supplying water to all areas, under testing.

  • The pipe and related materials for the 600 mm main pipeline would be ordered by the next day.

  • Tanker services would change as the water services were reconnected, and would continue until further notice while the network was tested.

The Municipality thanked residents for their patience and noted that water was being delivered through the alternative backup network. Permanent repairs to the 600 mm main pipeline and the water reclamation plant were still required, and the technical teams were preparing to start them as a matter of urgency. The same update was also shared that evening as a "Good News" notice.

Wednesday, 16 September 2026

  • Overall status: improved. With the 500 mm pipeline repaired, the network was back online and providing water to communities.

  • Gamka Dam: 100%.

  • Small pipelines: Brandwacht and Hans River pumping water to the reservoirs. Repairs had started on two other borehole supply pipelines, to be completed over the next two days.

  • Supply: initial reports indicated that all areas were back on the network with water at the taps. Some isolated cases were receiving attention.

  • 600 mm main pipeline: the pipe and related materials would be ordered that day.

  • Tankers: scaled down to three tankers in the areas that still had problems, mainly Mid-Town, Rustdene and New Town, until further notice.

The Municipality described the update as very positive and thanked residents, as well as its own teams, for their service during this challenging period. Supply was still running through the alternative backup network, and permanent repairs to the 600 mm main pipeline and the water reclamation plant remained to be done.